The development board has accused builder BAM, based in Kill, of not properly resourcing the project to allow for its completion.
More than 12 thousand defects remain outstanding on the new National Children's Hospital project.
The development board has accused builder BAM of not properly resourcing the project to allow for its completion.
Chair of the development board, David Gunning has rejected the suggestion from BAM the delay is down to design changes mid project.
It was supposed to be handed over today - 41 months late - with a new date expected tomorrow.

Worst Prison Overcrowding In History Of State, According To Prison Officers Association
Minister Martin Heydon Speaks As Fuel Scheme Announced
Sallins Man Part Of Intercepted Global Sumud Flotilla
One In Seven Households Unable To Afford Adequate Home Heating
Fifth Arrest Made In Connection With Fatal Edenderry Fire
Two People, Including A Teenage Boy, Arrested After Gun Incident In Ballymun
Man Charged With Fatal Assault Of Woman In Waterford
Fuel Support Scheme Announced, With Payments To Some Sectors Expected By June