The development board has accused builder BAM, based in Kill, of not properly resourcing the project to allow for its completion.
More than 12 thousand defects remain outstanding on the new National Children's Hospital project.
The development board has accused builder BAM of not properly resourcing the project to allow for its completion.
Chair of the development board, David Gunning has rejected the suggestion from BAM the delay is down to design changes mid project.
It was supposed to be handed over today - 41 months late - with a new date expected tomorrow.

Families Could Face €1,000 Rise In Annual Food Bills Amid Farming Crisis
Over Half of Cigarette Packs Surveyed In Newbridge And Naas Had No Irish Duty Paid
Celbridge Brewery CEO Warns Of Mounting Costs Facing Craft Beer Sector
Amhrán na Laoch Songwriting Competition Confirmed for Irish Music Month 2026
Government Announces Major Overhaul of Anti-Money Laundering Rules
Maynooth University Hosts Special Solar Eclipse Event This Evening
Johnstown Mother Says Today's Solar Eclipse Means Something Extra Special For Her And Her Son
Three Men Detained In Kildare And Dublin Garda Stations Following Brothel Keeping And Organised Prostitution Arrests