6 Footpath Construction Projects Begin In The Naas MD This Week.

Stock Image: Pixabay

Traffic management systems will be in place in all locations.

Footpath construction works begin in 6 locations in the Naas MD this week

Kildare County Council is warning that some may cause delays to traffic, and traffic management systems are in place for all of these works projects.

Works begin at the Woodlands Estate/Tipper Road Junction this morning, and are not scheduled for completion until October 15th.

Another project, at Railway Terrace, also starts today, and will take 5 days to complete

On Tuesday, works begin at the Townhouse Hotel, Newbridge Road, and will continue until Friday.

On the same day, path widening and up-grade work begins on the Sallins Road, from The Orchard to Oldtown Demesne.

They'll finish up on October 8th.

Another project, at Lacken View, also starts tomorrow, and should take 5 days to finish.

All works will begin, daily, at 8am, and continue until 6pm.

 

 

 

 

More from Local News

Stay tuned to Kfm!

Get the Kfm Apps for you phone, tablet or smart speaker...

Kfm Kildare Weather

  • Fri

    Light rain shower

    11°C

  • Sat

    Sunny intervals

    11°C

  • Sun

    Sunny intervals

    12°C

  • Mon

    Sunny intervals

    11°C