The remaining 12 units are expected to be delivered by the end of June.
Kildare County Council's has confirmed the time-frame for delivery of the Respond Homes in Flinter's Field in Athy.
It follows a query brought forward by Fianna Fail Councillor and Athy MD Cathaoirleach, Brian Dooley.
The time-frame for the delivery of these units is as follows:
• First 23 units are expected to be delivered by late February.
• Remaining 12 units are expected to be delivered by the end of Quarter 2 2023.
Kildare County Council did however state that these delivery dates are "approximate, and are dependent on there being no delays caused by adverse weather conditions, utility connection, resources etc."

Kildare Woman Forced To Urinate In Car Park As TD Pushes Law For ‘No Wait’ Toilet Access
Dublin Jersey Among Tributes To Ryan Weir Gibbons - Death “Unnecessary And Tragic” Says Priest
Three Decades Later, Search For Answers In Jo Jo Dullard Case Continues
Kildare County Council Targets Unused Housing Sites With Planning Permission To Speed Up Construction
EU Environment Commissioner Visits Kildare Farm Ahead Of Nitrates Derogation Talks
Defence Forces Conduct Readiness Exercise At Whitewater Shopping Centre In Newbridge
Call For Sanitary Bins In Men’s Toilets To Support Prostate Cancer Survivors
Own-Brand Foods Often Produced By Same Factories As Big Labels, Says Money Doctor John Lowe