There are 28 such legacy sites in Kildare, in all.
A remediation plan is being developed for a Kildare legacy landfill.
These are landfills operational between 1977 and 1997, which have now been regularised.
There are 28 legacy sites in Kildare, in all.
A risk assessment reveals 7 sites are classed as high risk, 11 as moderate risk and 10 as low risk.
KCC was allocated funding in 2019 to conduct additional assessments of two sites, at Knocknagarm and Pollardstown.
The council has now tendered for the provision of an Environmental Risk Assessment and Remediation Plan, including ground investigations, for Knocknagarm, on The Curragh.
It is deem a high risk site.
The deadline for the response to the tender is July 23rd.

Water Outage In Place For Maynooth And Straffan Tomorrow
Kfm Obituary Notices
Nationwide Fuel Protest Continues Into Third Day
"I Don't Think Anybody Is Going To Really Listen To Us Until Somebody Dies On That Road": Criticism Of Moone-Timolin Cycleway Continues
International Wholesale Prices Are "Not Price Gouging", Says CCPC
Costs Of Home Heating Oil Up By 67.5 Per Cent Between February and March
91-Year-Old Lelia Doolan To Arrive In Monasterevin Today As Part Of Her Walk For Peace
Over €400,000 Awarded To Repair And Protect Three Kildare Heritage Structures