Phase 1 begins today & is expected to be completed by 23rd of January
Upgrades to Sallins wastewater network have begun this morning.
The works, will be delivered on behalf of Coffey Construction Limited.
Some roads in the village are closed, but traffic management is in place, with emergency & restricted local access maintained.
Irish Water says that Phase 1 begins today and is scheduled to be completed by the 23rd of January.
Phase 2 is to begin on the 24th of January, and is scheduled for completion on 13 February.
Schedule permitting phase 3 is to begin on the 14th of February, and is due to be completed by the 6th March.
The utility company notes Sallins, Clane, Naas, Newbridge and Kill were served by a wastewater network which was no longer fit for purpose, leading to overflows and flooding during storms.
Irish Water says it is investing over €38 million to solve the problem & provide additional capacity to support the building of houses, schools, attract new industry and allow companies to expand and grow.

Department Of Housing Shifts Blame On To Council As Kildare Families Priced Out Of "Affordable" Housing Again
Outbreak Of Bird Flu Has Been Confirmed In Carlow Turkey Flock
Lidl To Open Country’s First Net Zero Energy Store In Maynooth This Thursday
Contract For Maynooth Eastern Ring Road Project Awarded To Company Based In Kilcullen
Policy Shift Allows Private Sector To Construct Wastewater Plants For New Housing
End Of An Era At Berney Bros Saddlery In Kilcullen As Master Craftsman Retires After 51 Years
Parents Invited To Take Part In Major Survey On Primary Education’s Future
€102,600 Granted For Repairs To The Ballymore Eustace Liffey Linear Golden Falls Loop Walk