Critical repair works by Uisce Éireann on a key water pipeline serving Kildare has now been completed, with normal operations now resuming.
Critical repairs to the Ballymore Eustace to Saggart trunk watermain have been completed, bringing to an end the largest repair programme carried out on the pipeline to date.
The watermain supplies homes, businesses and essential services across Dublin, Kildare, and parts of Wicklow.
More than 300 workers were involved in the operation, with the repairs finished within the planned 27-hour window.
Water is now flowing through the pipelines again and the network is returning to normal operation.
The works included replacing a damaged section of the pipe and repairing 15 leaks, with the aim of improving the long-term reliability of one of the region's most important water supply routes.

Clane Woman Awarded For Initiative Supporting Women In STEM Industries
Maynooth University Staff Set For Industrial Action Next Month
Kildare Senator Calls For Better Public Transport Connectivity Within Newbridge
Kildare Volunteers Remove 580KG Of Waste During Nationwide Clean Up Day
Luas Project For Lucan Set To Progress To Consultation Stage Later This Year
Raheens GAA Club Awarded €5K As Part Of Nationwide Campaign
Council To Re-Engage With Celbridge St. John Of God In Effort To Re-Open Car Park
Kfm Obituary Notices